Project:
|
Construction of two roundabouts on the B3 and construction of a cycle path linking Bernsdorf and Schönstadt. |
Client: |
Marburg Department of Roads and Transportation |
Construction period:
|
2008 |
Volume:
|
1.1 million euros total construction cost |
Performances:
|
Performance Phases 3 and 5 in accordance with HOAI |
Special aspects:
|
Two light-signal-controlled junctions (distance approx. 300 m) were replaced by roundabouts with the aim of improving performance and safety. A cycle path was also installed on one side of the B3. As it was necessary to utilise retentation space, surveys into compensating the losses needed to be carried out. |